UK construction framework calendar.
The major public sector construction frameworks, who runs them, where they are in their cycle and what each one means for a subcontractor. Last checked 25 October 2026.
Subcontractors do not usually bid for frameworks. The main contractor holds the place and brings its supply chain with it. What a framework calendar tells you is when a contractor’s supply chain is about to be built or refreshed, which is the moment a procurement team goes looking for firms in your trade and region. The supply chains guide covers what they check when they do; this page tells you when.
Since the Procurement Act 2023 came into force, frameworks can be set up as open frameworks that reopen to new entrants during their life, and public bodies publish pipeline notices for spend over £100m a year. That makes the dates below more useful than they used to be: a missed launch is no longer a four-year wait.
Twelve frameworks, where each one stands.
| Framework and operator | Coverage | Value | Where it is in the cycle | What it means for a subcontractor | Source |
|---|---|---|---|---|---|
| Construction Works and Associated Services 3 (RM6320), incorporating ProCure24 Crown Commercial Service and NHS England | UK wide, all public bodies | Up to £120bn over eight years | Bids closed 4 June 2026. Award and mobilisation expected December 2026 to March 2027. Runs January 2027 to January 2035. | Closed to new Tier 1 bidders. Watch the award list and approach the appointed contractors’ supply chain teams in early 2027, before their first call-offs. | Construction Intelligence |
| SCAPE Construction Works and Services Framework SCAPE | England, Wales and Northern Ireland | £8bn over four years, five sector lots | Tender notice published August 2026. Requests to participate closed 9 October 2026. Award expected 2027. | Delivery partners will be named in 2027. SCAPE frameworks run through a small number of partners, so getting onto their regional supply chains is the route in. | New Civil Engineer |
| SCAPE Regional Construction Framework SCAPE | England and Wales, regional lots | £1.2bn excluding VAT | Amended submission deadline 11 September 2026. Award to follow. | Regional contractors and JVs were able to bid. Appointed firms will need local subcontractors in each lot region. | Construction Magazine |
| SCAPE Scotland Construction Works and Services Framework SCAPE Scotland | Scotland, seven lots | £4bn over four years | Notice published 14 May 2026. Requests to participate closed 3 July 2026. Invitations to tender due 19 October 2026. | Scottish subcontractors should identify the shortlisted contractors now; appointments are expected in 2027. | The Construction Index |
| National Framework for Major Works 2026 Pagabo with YPO | UK wide, projects of £5m and above, five lots | Up to £5bn over four years | Tendered 27 April to 22 June 2026. 56 suppliers appointed October 2026. Live now. | Live. Morgan Sindall, Wates, BAM and Clark Contracts are among the 56. Their supply chain teams are registering subcontractors for call-offs now. | Project Scotland |
| National Framework for Civil Engineering, Infrastructure and Enabling Works 2026 Pagabo with YPO | UK wide, 13 lots split by region, including demolition, remediation and groundworks | Up to £4bn | Tender deadline 12 June 2026. Award and commencement September 2026. | The most relevant framework on this list for groundworks, demolition and civils subcontractors: the enabling works lots are regional and the appointed contractors will subcontract most of them. | Find a Tender |
| Developer-Led Framework (second iteration) Pagabo | UK wide | Up to £26bn | Eight-week bidding window opened 11 May 2026. Award to follow. | Developer-led schemes bring their own supply chains; the route in is through the appointed developers and their main contractors. | Pagabo |
| Construction and Refurbishment Framework Fusion21 | UK wide, housing and non-domestic lots | £750m | Market engagement closed 20 October 2026. Tender notice expected by 12 November 2026. | Open now to bidders. Fusion21 has said it wants SME and local participation, so regional contractors in housing refurbishment should watch the November notice. | Construction News |
| North West Contractor Framework (third iteration) Procure Partnerships for Wirral Council | North West England, 13 lots from £50k to over £100m | £1.2bn including VAT | Live from 1 April 2026 to 31 March 2030. 53 contractors appointed. | Live. Kier, Wates, Morgan Sindall, GRAHAM and regional firms such as Krol Corlett and City Build hold places; the lower-value lots are where regional subcontractors are most used. | Procure Partnerships |
| North West Construction Hub High Value Framework 2027 to 2031 Manchester City Council | North West England, high value | Up to £1bn | Tender submissions closed 1 June 2026. Award notice expected November to December 2026. Starts January 2027. | Appointments due within weeks. The new partners will be building supply chains for January starts. | Procter and Street |
| YORbuild3 Minor Works and YORbuild Major Works 2 YORhub | Yorkshire and Humber, North and North East Lincolnshire, Sheffield LEP area | Minor Works up to £4m; Major Works 2 over £10m | YORbuild3 Minor Works expired July 2026 with an option to extend by two years. YORbuild3 Major Works expired April 2026 and has been replaced by YORbuild Major Works 2, which is live. | Check which contractors hold Major Works 2 places; a re-procurement of Minor Works is likely during 2027 or 2028. | YORhub |
| Construction Works Framework NEPO | North East England, projects from £100k to £70m | £800m | Runs until June 2027. 24 contractors, 11 headquartered in the North East, including Brims, Esh Construction, Surgo and T Manners. | Expect re-procurement notices in the first half of 2027. North East subcontractors should be on the supply chains of the current 24 before then. | NEPO |
Dates are taken from the linked notices and reports on the day shown above. Always confirm on Find a Tender or the operator’s own site before acting on them.
What to do when a framework on this list moves.
Find the appointed contractors
The operator publishes the list. Pick the ones active in your region and sectors, find their supply chain registration route, often Constructionline, and register with the same evidence your website carries.
Help a contractor you know to bid
Bidders score better with named supply chain partners, social value and local labour. A subcontractor with a case study in PQQ format and a capability statement is useful to them at this stage.
Get on the current supply chain first
Incumbents usually keep their places. Being on their list before the re-procurement means you carry across; a new entrant has to be found and verified from scratch, which is where your website is checked.
Questions this raises
Can a subcontractor bid for a framework directly?
Rarely. Most construction frameworks appoint main contractors who then procure packages from their supply chains. Some specialist frameworks, for example the enabling works lots on the Pagabo civils framework, appoint specialist contractors directly, and a larger subcontractor can bid for those.
What is an open framework?
A framework set up under the Procurement Act 2023 that reopens to new suppliers at set points during its life, rather than closing for four years at award. Operators state in the notice whether a framework is open.
How do I find out which contractors hold a framework place?
The operator publishes the appointed list on its website, usually in a user guide, and the award notice on Find a Tender lists them. The sources linked in the table go to those pages.
How often is this page updated?